OpenAI’s six-building Georgia plan advances. Patmos plans an Alabama Walmart conversion. Google signs for 50MW of geothermal power. Valor buys Ohio computing center. Two data center deals.

Good morning. Welcome to Data Center View! In each issue, we cover the top stories, trends, and listings in the data center sector.

→ Make someone’s day! Forward Data Center Daily to clients and colleagues. They can sign up here.

Now, let’s get to it.

NEWS ROUNDUP

Stock data center interior with ChronoScale logo and Odessa, Texas label

FINANCING: ChronoScale agrees Odessa, Texas AI campus venture and up to $750M financing. ChronoScale has signed agreements for a 50/50 partnership with STN to develop a planned 350MW campus. The first 65MW is ordered by an unnamed frontier AI lab for deployment in the first half of 2027, with up to $7.5 billion in contract value over six years. The remaining 285MW is subject to further orders. ChronoScale, led by CEO Cenly Chen, will manage the venture; STN, led by CEO Sabur Mian, will lead campus development.

Stock server racks with OpenAI logo and Effingham County, Georgia label

DEVELOPMENT: Effingham County approves OpenAI’s six-building data center plan in Georgia. Commissioners unanimously approved the site plan for Project Camellia, a roughly 1,400-acre campus at Savannah Gateway Industrial Hub. The plan includes six data center buildings, two substations and cooling infrastructure. Project engineer Aakash Verma said the revised building configuration would improve emergency access and construction speed without increasing power or water use. Construction still requires further county approvals, and work affecting wetlands requires a federal permit.

Stock data center equipment with Patmos logo and Fairfield, Alabama label

DEVELOPMENT: Patmos plans data center at former Walmart in Fairfield, Alabama. Patmos plans to convert a 205,000-square-foot former Walmart into a technology campus with 20MW of initial capacity and potential expansion to 50MW of utility capacity. Initial operations are targeted for May 2027. The company has agreed to terms with Alabama Power and will cover the full cost of serving its energy needs. CEO John Johnson said the project will reuse an existing building to support a mixed-use technology campus.

Stock data center interior with Google logo and The Dalles, Oregon label

ENERGY: Google signs 50MW geothermal power agreement with Quaise for Oregon data centers. Google will purchase 50MW from Quaise Energy’s planned Project Obsidian in Central Oregon, with delivery beginning as early as 2030 to support its data centers in The Dalles. The initial phase will use conventional drilling; a second phase is planned to use millimeter-wave technology. Quaise CEO Carlos Araque said the agreement establishes a commercial foundation for superhot geothermal. Google’s advanced energy head Lucia Tian said the partnership will support a more robust and affordable energy supply for Oregon.

DATA CENTER PROPERTY FOR SALE

Click on each photo for more information.

Broker photograph of 785 Greens Parkway, Houston, Texas

785 Greens Parkway, Houston, TX 77067

124,480 SF | 10.01 Acres | Vacant Building for Data Center Conversion | Proposed ~4MW, Expandable to ~20MW | Contact Brokers for Pricing

Broker aerial of 2212 Elrod Road, Katy, Texas, showing leased bitcoin mining premises and excess land

2212 Elrod Road, Katy, TX 77449

Leased Bitcoin Mining Facility | 23.22 Acres | Absolute NNN Lease Through March 2032 | ~13.22 Acres Excess Land | $10,400,000